Construction
CQ Operations
SEQ Operations
|
Kogan Creek Power Project – Boiler
Construction
|
|
CBH
are contracted to Babcock-Hitachi K.K., Japan to undertake the
construction of a 750 MW supercritical coal fired boiler for the Kogan
Creek Power Project.
|
|
In
January 2005, CBH commenced mobilisation of our site facilities,
construction equipment and construction workforce.
First
steelwork erection occurred during June 2005. The
construction program established for the project is the shortest ever
planned for an Australian power station and in particular this is the
largest single generating unit in Australia.
The Top
Girders are due for positioning in August 2005 and the erection of the
pressure parts will follow.
Our
construction activities are planned for completion in early 2007.
An
accommodation facility at Chinchilla will house a majority of our
workforce engaged on the boiler erection. Other employees are sourced
from the local Dalby/ Chinchilla region.
|
 |
Pioneer Sugar Mill – Boiler No. 2 Upgrade
|
|
CBH are
nearing completion of a major boiler upgrade on a Babcock & Wilcox bagasse
fired boiler at Pioneer Sugar Mill.
This
project is associated with CSR Sugar Mills’ Cogeneration Plant at Pioneer
Mill.
We were
awarded the contract in late July 2004 and executed the design, supply,
construction and commissioning of the upgrade on a Fee/ Reimbursable/ Target
Cost basis under CSR Sugar Mills EPCM, United KG. An aggressive programme
was established by CSR and CBH approached the contract in an open and
cooperative spirit in order to achieve CSR’s objectives.
|
|
The scope
included additional Pressure Part waterwalls for increased furnace sizing,
new superheater, FD Fan, ID Fans, FD and ID Ducting, Boiler Feed Pumps,
Deaerator, Supporting Steelwork, Access Galleries and Stairways, Valves,
Instruments, Piping and Supports.
Our
experienced Project Team both on and off site demonstrated their expertise
under some very exceptional circumstances that occurred during a number of
phases of the contract.
|

Before Construction
|
|
 During Construction
|
CBH Site
Management, Supervisors and Construction workforce engaged on the
construction were chosen from our very large pool of skilled tradesmen with
proven competence. These resources were supplemented by our experienced
Commissioning team.
During
the part dismantling and re-construction of the existing boiler, CBH
maintained an excellent safety record together with a high quality level of
workmanship.
|
|
This
project was unique, as major design changes were required to the B & W
Boiler to increase steam output to 240 tonnes/ hour and improve boiler
efficiency. In addition, reduced particulate emissions from the Stack were
required to satisfy EPA requirements. The provision of horizontal Wet
Scrubbers was incorporated to reduce emissions.
|
 Near Completion
|
Queensland Nickel Industries, Townsville – Major Boiler Refurbishment
|
|
CBH has
recently completed a major refurbishment for the second of three (3) oil
fired boilers at QNI’s Nickel Refinery at Yabulu, near Townsville.
Refurbishment of Boiler No. 1 was extensive on these Mitsubishi boilers and
included complete pressure part (waterwalls and headers) replacement,
Superheater, finned tube Economiser, Oil Burners, casing, Air and Gas
Ducting, Insulation and Cladding, integral piping, valves, access platforms
and stairways. Boiler No. 2 was a major overhaul of similar scope, but to
a lesser extent than No. 1 with only partial replacement of pressure parts.
|
|